Small update.
Portacabins have arrived, but they are actually TFL people on site. Basically they will be doing the work for the new tube entrance before work on the scheme can proceed. That work is expected to be completed by June 2016.
Once done, t…
They sell them in phases. It isn't in the developers interest to sell them all years before completion.
During the launch I believe they had about 50 properties for sale, but judging by the listings on Right Move some buyers/investors requested flat…
@NorthNineteen Correct
@Arkady I receive occasional updates via email and post. From memory the original estimate was staged completion throughout 2017, with a long date of 2019.
Long time lurker. First time poster
The latest on City North is that terms couldn't be agreed with their preferred contractor, so they have gone back to the tendering process.
Estimated completion is now 2019
Source: I bought off plan